Addition Construction Resumes

Well, shortly after my post on Monday, trucks began arriving, delivering the ICF units that will be used for our foundation/basement walls. There are a lot of them piled up all over.

ICF forms in the back yard, as seen looking down from the upper veranda

ICF forms in the back yard, as seen looking down from the upper veranda

More ICF forms in the side yard and along the lower driveway. You can also see one of our Japanese beetle traps in the foreground, they've been fierce this year.

More ICF forms in the side yard and along the lower driveway. You can also see one of our Japanese beetle traps in the foreground, they’ve been fierce this year.

Monday they also put in the front foundation drain and tidied up the grade inside the foundation. Yesterday was rainy and therefore contractor-free. Today more gravel is being delivered for use as backfill and under the basement floor.

Plus, the windows we had ordered from Lowe’s arrived on Saturday, they have been stored in the cellar (with the large patio door under the veranda.)

Oh, and I ordered the two garage doors (one 8′ wide and one 6′ wide) today from Home Depot, they were 15% off, and the Lowe’s doors did not allow windows in the narrower 6′ door, among other things.