Addition Omnibus Progress Late Winter 2017 [Video]

Forgive me, for I have sinned: It has been almost a year since my last post. We made good progress on our (seemingly interminable) addition project over last spring and summer. I took a lot of pictures with many blog posts in mind, but, well, «insert aphorism about the surface of a road to a […]

Addition Early-Spring Progress

Addition Ready for Final Concrete Pour

Well, almost, still have to do the final cleanup. We are trying to arrange the final concrete pour, but with winter on the way the concrete tradesmen are very busy trying to get their outdoor pours done. This pour is about 1068 square feet and will be 4½ – 5 inches thick. It is being […]

Addition Update, Day 434 (Ouch!)

As I said in an earlier post, we got delayed in our construction over the summer. We got a six-month extension on our building permit, so mid-December is our new target for completion. Still lots to do, but now that the hot weather has broken I am able to get more done. My #1 priority […]

Addition Solar Heat Plan

The underfloor hydronic heat in the addition will consist of 3 zones with 4 loops total: basement 1-loop zone, great room 2-loop zone, and under-loft 1-loop zone. Each loop is 300′ 5/8″ PEXa tubing. The expectation is that the great room zone will the most active. The intention is to run each loop at 1.75 […]

Addition Progress Report, Week 32

Slow progress lately, working around the snow/ice/cold, but progress nonetheless. The plumbing rough-in is done, as is the main floor electric. Stairs are in, drywall about 75% up but not yet mudded. Exterior siding also at 75%. Next week, hopefully, wallboard should all be up and the attic insulation should be in. Then after the […]

Addition Progress Report, Week 29

Also, some of the plumbing has been roughed in and most of the basement wallboard is up, but pics will wait for another day.

Addition Progress on the Inside

Over the holidays the roofers completed the metal roof, and the insulation sub did round one on the inside of the exterior walls: sprayed 1" closed-cell urethane foam followed by fiberglass batts. Then last week the general contractor crew came in and did some wallboard. They did what they could while still leaving space for […]

Addition Progress from the Outside

Christmas Eve day was busy around here with four different construction-related visits: framers, to complete a few odds and ends; electrician, ditto; a debris-removal visit; and an inspector, who OK’d the framing and electric. The day before the roofers got started on the metal, as seen below from the pasture.

Addition Progress Slow But Real

Well, for the past month there has been progress. All the windows and exterior doors are in place. The first round of electric wiring rough-in has been done. The roofers should be here (maybe this week) to put the metal roof on. Next up is the plumber.

Addition Windows Start Going In

Addition Update: Roof Trusses

Been busy around here the last week and a half.

Addition Framing Begins

New Addition Update, Month 3

It has been almost a month since my last post about our new addition. Work has been proceeding, albeit slowly at times. It was always a long-shot that we would be (mostly) done by winter, and that long shot is missing widely. Now our sights are set on getting it under roof and closed in […]

Addition Foundation Forms

Well, after a series of frustrating delays, the foundation (basement wall) forms are ready for concrete. I also treated myself to a fancy new toy: A DJI Phantom Vision 2 Plus quadcoptor drone – a flying camera! I just started flying it yesterday, here is a new perspective on our construction — bonus points if […]